Australian Competition and Consumer Commission Office Fit-out

On behalf of the ACCC, OPRA Projects completed a high-end office fit-out accommodating 34 workstations, reception, breakout space and associated boardrooms, quiet rooms and offices.

Early and thorough reviews were conducted with each relevant trade due to the level of detail across the security specification, contract documentation and the Zone 3 security requirements. All elements of the brief were communicated to sub-contractors, who identified buildability issues early in order to provide alternative solutions. This was instrumental in successfully meeting the requirements on the accelerated programme. Practical completion was therefore achieved two weeks earlier than originally tendered.

Working within the Quadrant Building – one of Perths premium providers of office accommodation – also posed it’s own challenges. Maintaining business continuity for the building and its users was critical to the projects success which resulted in out of hours work and close liaison with facilities management.