OPRA Projects, in collaboration with our interstate partners Hunter Mason, were engaged as part of a national roll-out to deliver four specialist counselling centre fit-outs, totalling 2,200sqm and located across three states.
The Rockingham branch consisted of a new spec fit-out with some demolition and minor structural works, new services facilities, a new workstation area, new reception, new consultation rooms, and a new breakout area.
OPRA incurred some on-site delays with EOT’s and a 2-week extension was awarded. The client requested the project to be handed over one week earlier to allow staff to move in sooner. OPRA delivered the project one week earlier than the revised contract programme.